Public Road / Utility Construction Policy
The City’s policy on the construction of future
public improvements is as follows:
Any development that contains public roads or
utilities must have a minimum level of city involvement in order to
be handed over to the City upon completion. Upon receiving planning
commission approval of a plat, site condominium, planned unit
development, etc, the developer shall provide the City Engineer with
plan and profile drawings (3 sets) of all proposed public
improvements. These plans shall be 1" = 40’ scale (profile view 1" =
10’) drawings with all the necessary detail for bidding and
construction. The City Engineer shall have 3 weeks to review the
drawings and provide a check print to the developer. The developer
shall resubmit the revised drawings along with the check prints for
final approval. A mylar copy of the cover sheet should also be
provided for signature by the City Engineer.
Prior to the Walker City Engineer signing the plans,
the developer shall provide a cost estimate (stamped by a
professional engineer) and inspection deposit to cover the cost of
inspection and construction administration. The calculation for the
deposit shall be based on Inspection Escrow Deposit policy and
formula (roughly equivalent to 15% of the sanitary and water cost
plus 8% of the improvements and drainage estimate). If the project
is privately funded, the developer may bid the project privately.
The developer and his contractor will schedule a preconstruction
meeting prior to beginning work on the public improvements. At this
meeting the City Engineer will direct Walker’s inspection /
consulting staff to oversee all phases of the project construction
through completion. This includes working with Grand Rapids on the
approval of sanitary sewer and watermain. Walker staff or
consultants will submit all construction documentation to Grand
Rapids in an effort to bring these utilities into service.
The developer will be responsible for providing a
construction engineer on the project to answer routine questions
from the contractor and communicate with Walker’s inspection staff.
Any changes to the plans, however, must be reviewed and approved
with the City Engineer. Any change or modification should be
proposed by the developers engineer and formally submitted with 3
sets of plans.
The City shall use the inspection escrow deposit for
the following:
-
Consultant inspection services
-
Consultant construction engineering/administration
-
City of Grand Rapids construction
engineering/administration
-
Consumers Energy street light installation (if
applicable)
-
Any independent geotechnical investigation
required by the City Engineer
If off site improvements are required for a
development the City may wish to take on the design and bidding
requirements. This would include off site sewer or watermain greater
than 600’ in length, any sanitary sewer or watermain that is
considered a trunk utility (sized to handle additional flow),
offsite road work that is greater than 100’ in length or requires
special assessments, or reconstruction of any existing public
infrastructure. In these cases, the City Engineer shall cause a cost
estimate to be prepared for the public work. This funding for this
work, including reasonable contingencies, should be incorporated
into the development agreement and placed in escrow with the City of
Walker prior to executing the agreement.
For purposes of this policy, offsite improvements
shall be defined as extending any infrastructure outside of the
property boundary for the project. Any perpendicular connections to
roadways, sewers, or watermain will not be considered off site
improvements.