Construction Updates
3 Mile Over Indian Mill Creek Bridge Replacement
Davis Construction has completed most of the work associated with the
3 Mile Rd. bridge replacement over Indian Mill Creek. Over the
last 100 days, they have reconfigured underground utilities, removed the
90 year old structure, replaced the concrete arch bridge, and installed
the roadway over the bridge. The final 2” surface layer of
pavement could not be completed due to extremely cold temperatures.
The contractor will come back in late spring and place the additional
layer of asphalt on the roadway along with permanent pavement markings.
The roadway will be open through the winter and spring with no
anticipated restrictions to access or weight.
Work for this project began 250’ west of Indian Mill Creek and
extended 600’ east to the west side of the Coopersville/Marne Railroad
bridge. The new bridge is wide enough to accommodate a future 5
lane roadway section. New sidewalk was also installed along the
project corridor. Due to cost limitations, the existing railroad
bridge was not adjusted or modified as part of this project.
Government |
Departments | Community
| Resource Center
Contact Us |
Search |
Site Map |
Home | Site Use Policy
The City
of Walker, Michigan
4243 Remembrance Rd. NW
Walker, MI 49534
(616)453-6311
Effective April 9, City Hall will be open Monday through Thursday from
7:30am to 5:00am,
and on Fridays from 7:30am to 11:30am.
All information © 2012 City of
Walker
Contact Us!
If you would like to leave general
comments about the website, click here.
Click here to report technical problems with the website.
|