Construction Updates
Indian Mill Creek Bridge Replacement
3 Mile Rd will be closed at Indian Mill Creek from
September 1st - December 12th for a bridge replacement project.
The project will address the 90 year old structure that
carries 3 Mile Rd over Indian Mill Creek. The work will begin 250’
west of Indian Mill Creek and extend 600’ east to the west side of the
Coopersville/Marne Railroad bridge. The new bridge will be wide
enough to accommodate a future 5 lane roadway section. The project
corridor will also have new sidewalk installed as required. The
existing railroad bridge will not be adjusted or modified as part of
this project.
The official detour will be Fruit Ridge Ave and Walker
Ave to I-96. Local traffic may also take advantage of alternate
routes.
Fred Meijer Standale Trail
Updated August 13, 2010
Maynard and O’Brien:
Storm sewer on Maynard, south of O’Brien, has been installed.
Retaining wall construction on Maynard, south of O’Brien is complete.
Asphalt base has been installed on the northern half of Maynard, south
of O’Brien.
Trail construction on Maynard, south of O’Brien is expected to be
complete by the end of August.
Work on Maynard, north of O’Brien is scheduled to begin in early
September.
Work on O’Brien is scheduled to begin in the middle of September.
Consumers - Maynard to Sunset Hills:
Boardwalk construction is mostly complete.
Grading is underway.
Asphalt paving is scheduled to begin in the next few weeks.
Consumers - Lake Michigan to Leonard:
Boardwalk construction is mostly complete.
Grading is complete.
Asphalt base has been paved.
Asphalt top course is scheduled to be paved in the next few weeks.
Consumers - Leonard to Remembrance:
Boardwalk work is scheduled to resume in the next few weeks.
Grading is scheduled to begin in the next few weeks.
Remembrance
Trail has been paved from Justin to the existing sidewalk near
Richmond.
Utility pole relocations along Remembrance, north of Kinney, are almost
complete.
Trail paving from the existing sidewalk near Richmond to City Central
Park is scheduled for September.
Note: The work schedule presented above is based upon best estimates.
Since the schedule is dependent upon weather and other factors, it is
subject to change.
Construction Photo Gallery
| August 13, 2010 |
 |
 |
| July 7, 2010 |
 |
 |
| May 27, 2010 |
 |
 |
| April 29, 2010 |
 |
 |
| |
|
| |
Government |
Departments | Community
| Resource Center
Contact Us |
Search |
Site Map |
Home | Site Use Policy
The City
of Walker, Michigan
4243 Remembrance Rd. NW
Walker, MI 49534
(616)453-6311
City Hall hours: Mon-Thursday from 7:30am to 5:30pm. Closed Fridays
All information © 2010 City of
Walker
Contact Us!
If you would like to leave general
comments about the website, click here.
Click here to report technical problems with the website.
|